A Capital Projects Update
Progress is Underway at Selah High School!
If you’ve driven past the athletic fields at Selah High School recently, you may have noticed exciting changes underway. Earlier this spring, construction began on the field upgrades to the outdoor athletic facility at Karl Graf Stadium. Also this spring, the Selah School District Board of Directors approved moving forward with the new Career and Technical Education (CTE) addition incorporated into the high school campus. As the vision for Selah High School and the District comes into focus, these two capital projects represent an investment in safe, modern, and future-ready spaces that will expand learning opportunities for students and strengthen the Selah community — all at no additional cost to taxpayers.
These two projects will expand opportunities for students both inside and outside the classroom while reflecting the community’s ongoing commitment to top-quality facilities that support every student.
To help bring these projects to fruition, the District relied on its long-range facilities plan developed with input from staff, parents, patrons, and community stakeholders. Improvements to Karl Graf Stadium and a new Selah High School CTE addition have long been included in the facilities plan and identified as priority projects in the first phase of the District’s long-term vision.
Importantly, both projects are being funded without a tax increase or new bond measure. Through a combination of existing capital project funds, state assistance, and endowment resources from the Wilbur Repp Estate, the District is able to move forward with approximately $8.1 million in improvements while continuing its commitment to responsible financial planning.
“It’s exciting to see these long-planned projects moving from vision to reality,” said Associate Superintendent Chris Scacco. “These improvements will create lasting opportunities for students while continuing our commitment to responsible stewardship of community resources.”
One funding source for both projects includes District capital fund dollars. Capital funding is restricted to capital projects such as facility improvements and cannot be used for operational expenses like salaries or staffing. While each project draws from multiple funding sources, this approach ensures the funds are used as originally intended.
Field turf installation work at the stadium began on April 13, in partnership with the contractor FieldTurf. The new turf will provide a safe, durable, and high-quality athletic space for participants while extending the field’s lifespan and usability. This upgrade is not only designed with safety in mind, but also built to withstand constant use by students and the community. Work will continue throughout the summer with installation targeted for completion by August and the fall sports season.
The total projected cost is $3,182,679, funded through the District’s Capital Projects Fund, including remaining state match dollars from previously approved safety-related improvements.
Looking at the District’s second scheduled capital project, groundbreaking of the Wilbur Repp Tech Center is targeted for June. Goodman and Mehlenbacher Enterprises, Inc. dba GAME, Inc., has been selected as the project contractor and will oversee construction of the state-of-the-art CTE facility integrated into the high school campus.
Repp, a 1953 Selah High School graduate, left a lasting gift to the District, dedicating a significant portion of his estate to support student opportunities and future career pathways. His vision aligns closely with the District’s growing Career and Technical Education program, which provides students with hands-on learning experiences and exposure to high-demand career fields. The facility is designed to expand opportunities for students pursuing both skilled trades and career-focused technical pathways.
The new facility will extend beyond traditional classroom spaces, offering modern, industry-style learning environments for programs such as agriculture, mechanics, construction, metalwork, machinery, and welding, among others. Designed to support 21st-century skill development, the center will help prepare students for both college and career opportunities after graduation.
“The Wilbur Repp Tech Center will provide students with meaningful hands-on learning experiences that connect directly to future careers,” said Superintendent Kevin McKay. “This project represents an investment not only in facilities, but in the future success of our students and community.”
The projected cost of the Wilbur Repp Tech Center is $4,927,427. Repp’s original $3.65 million donation — which has continued to grow through investment earnings — will fund nearly the entire project, with approximately $4 million available for construction. The remaining balance will be covered through state assistance and District Capital Fund dollars.
With visible progress now underway, the vision outlined in the District’s long-range facilities plan is becoming a reality — combining responsible financial stewardship with safe, modern spaces where students can learn, compete, and prepare for future success.